FLTF News

suealabonville

If you missed the Four Lakes Task Force webinar on January 22, you can view it at this link. Construction status at each dam was summarized and many questions were answered.


FLTF issued a News Flash (Feb 3, 2025) explaining the Tittabawassee River has returned to its natural path at the Sanford dam. Crews removed the cofferdams upstream and downstream of the dam that have kept the area dry while crews worked on the primary spillway and low-level outlet.


The News Flash also stated the importance of February 18, 2025. "If Heron Cove Association does not file an application for Leave to Appeal [by 2/18/25] FLTF can obtain financing for construction and dam restoration will resume." However, until there is an end to the Heron Cove Association legal challenges, FLTF cannot finance restoration.


Click here to read the News Flash for further details and see pictures of construction progress.

2 views0 comments

Recent Posts

See All

Introduction to the 4LakesForward Campaign

In an effort to keep our Sanford Lake Association members up to date, and fully informed, we are sharing the following information in the...

FLTF December Webinar Rescheduled

The next FLTF informational webinar has been changed to Wednesday, January 8, 2025 from 5-7:00pm. You can register here . They hope to...